Road Work – Highway U-144, Old Highway 91 & Dammeron Valley

The following are construction or maintenance work on roads within Washington County:

  • June 27, 2016 – June 30, 2016, Dammeron Valley West Side
    Washington County Roads will be sweeping all roads in the Dammeron Valley West Side in preparation for chip sealing.
  • June 29, 2016 – June 30, 2016 and July 5, 2016 – July 7, 2016, Highway U-144
    Washington County Roads will be sweeping Highway U-144 from I-15 Exit #42 to New Harmony Township Line by the cemetery including Harmony Heights subdivision phase 2 including 400 E., 200 S., and 800 E. in preparation for chip sealing.
  • July 5, 2016 – July 7, 2016, Old Highway 91
    Washington County Roads will be sweeping Old Highway 91 from I-15 Exit #40 to I-15 Exit #36 in preparation for chip sealing.
  • July 11, 2016 – July 12, 2016, Dammeron Valley West Side Area
    Washington County Roads will be chip sealing roadways in the Dammeron Valley West Side Area. “Keep garbage cans 5 feet off of the roadway edges and NO parking on roadways or roadway edges.”
  • July 13, 2016 – July 14, 2016 and July 18, 2016 – July 19, 2016, Highway U-144
    Washington County Roads will be chip sealing Highway U-144 from I-15 Exit #42 to New Harmony Township Line by the cemetery including Harmony Heights subdivision phase 2 including 400 E., 200 S., and 800 E. “No parking on roadway edges.”
  • July 19, 2016 – July 20, 2016, Old Highway 91
    Washington County Roads will be chip sealing Old Highway 91 from I-15 Exit #40 to I-15 Exit #36. “No parking on roadway edges.”
  • July 26, 2016 – July 28, 2016, Dammeron Valley West Area
    Washington County Roads will be sweeping all loose chips off of roadways in the Dammeron Valley West Area.
  • July 27, 2016 – July 28, 2016 and August 1, 2016 –August 4, 2016, Highway U-144
    Washington County Roads be sweeping all loose chips off of Highway U-144 from I-15 Exit #42 to New Harmony Township Line by the cemetery including Harmony Heights subdivision phase 2 including 400 E., 200 S., and 800 E.
  • August 8, 2016 – August 10, 2016, Old Highway 91
    Washington County Roads be sweeping all loose chips off of Old Highway 91 from I-15 Exit #40 to I-15 Exit #36.
  • August 12, 2016, Highway U-144
    Straight Stipe will be painting all roadway markings on Highway U-144 from I-15 Exit #42 to New Harmony Township Line by the cemetery and Old Highway 91 from I-15 Exit #40 to I-15 Exit #36.

* All Road Work have the same start and end time during specified days listed above.

Start Time: 7:30 AM
End Time: 6:00 PM

If you have any questions or concerns, please contact Washington County Road Department at (435) 634-5736.